Daily report & productivity metrics
Learning objectives
- Read a daily report as an account of working hours: production at the crew’s rate (Figure 5.2 or 4.1) and downtime by cause, weather, equipment, HSE, permits and standby
- Build the progress curve against the plan and forecast completion at the rate to date, , or if the rest goes to plan
- Find the downtime a plan can absorb, , and how many days of the plan’s production a crew is behind
- Compute what a lost hour costs in days, , and explain why each further point of downtime costs more than the last
A crew reports its production every day. Whatever the report’s format, at its core is an account of the previous day’s working hours: how many were spent producing, and so how many VPs (on land) or shots (at sea) were added, and how many were lost, and to what. Figure 6.6 sorts the lost hours into five causes: weather, equipment, HSE (health, safety and environment stand-downs), permits (waiting for access) and standby. Added up day after day against the plan, these few numbers say whether the survey will finish on time, and what each lost hour has cost.
In Figure 6.6, start on day 20 of a 30-day plan for 50,000 VPs, shot by two vibroseis fleets flip-flop for 12 hours a day; change the downtime shares, the crew and the report day, and watch the day’s report in (a), the progress curve in (b), where the hours went in (c) and what downtime costs in (d). The downtime shares are yours to set: the figure’s defaults illustrate the arithmetic and are not industry figures.
Hours make VPs
While it is producing, a crew shoots at a rate set by its method. Two vibroseis fleets shooting flip-flop with 12 s sweeps, 5 s of listening and 30 s move-ups fire a VP every 21 s, 171 VPs an hour (Figure 5.2); a vessel at 4.5 kn shooting every 25 m fires every 10.80 s, 333 shots an hour on line (Figure 4.1). A day of working hours could shoot , 2057 VPs for the vibroseis crew in 12 hours, and each bar in (a) is that potential, filled first with what was shot and then with what each cause cost. A plan for VPs in days needs a day, 1667 here: the dashed line in (a).
The figure draws each day from the shares you set. A whole day is lost to weather with the weather’s share of days; on a workable day each hour is lost to equipment, HSE, permits or standby with that cause’s share of the hours, or produces. With the defaults, 10 % of days and 15 % of the remaining hours, the downtime averages = 23.5 %. The first twenty days drawn do worse: three weather days, 36 hours, and 37 more hours lost to the other causes, 73 of 240 working hours, 30.4 %.
The progress curve and the forecast
Plate (b) adds up the VPs day by day against the plan’s straight line. By day 20 the crew has 28,629 VPs where the plan has 33,333: 85.9 % of plan, or 2.8 days of the plan’s production behind. The report forecasts completion two ways. If the rest of the survey goes at the rate to date, a day after days, the crew finishes on day
because a downtime leaves : day 34.9, 4.9 days late. If the rest goes exactly to plan, it finishes on day , day 32.8, late by the 2.8 days it is behind. The first assumes the downtime to date goes on; the second assumes the crew shoots the plan’s 1667 VPs a day from now on, more than the 1431 a day it has averaged. A forecast is only as steady as the days behind it: on day 5 the same crew’s rate forecasts day 38.4, and it finishes on day 33.3, with 27.0 % of its hours lost.
The downtime a plan can absorb
The crew and the plan enter the forecast only through and ; everything else enters through the downtime, and plate (d) draws . It meets the plan, , at
the downtime the plan can absorb: = 19.0 % here, less than the 23.5 % the shares average, so on these shares the crew is expected to be late before it starts, on day 31.8 in (d). A third fleet raises the rate to 212 VPs an hour (Figure 5.2) and the allowance to 34.4 %, and the same downtime then finishes on day 28.3. A plan that asks more than a day cannot be met at any downtime.
What a lost hour costs
An hour lost today would have shot VPs. They must be shot at the end, at the rate the crew achieves then, a day if it goes on as it has, so the hour costs
On day 20, with 30.4 % lost, each hour costs 0.12 days, 1.44 working hours: more than an hour, because the hours that make it up are lost at the same rate. Plate (c) multiplies each cause’s hours by it, so the 36 weather hours have cost 4.3 days. A vessel working round the clock pays about half as much for a lost hour, 0.06 days in the figure’s last exercise, because its day holds twice the working hours. And since grows as , so does its slope, : one more point of downtime over the whole survey costs 0.50 days at 30.4 %, and 0.80 days at the 45.0 % that a 20 % share of permit holds brings. Downtime costs most where there is already the most of it.
Reading a report
A day lost to weather is a bar in (a) with nothing shot and a flat step in (b); hours lost to the other causes shorten the filled part of a bar. The progress curve falling away from the plan’s line says the crew is behind; the forecast at the rate to date says how late it will finish if nothing changes; the allowance says how much downtime the plan had room for; and the hours by cause in (c) say where to act.